Report to the CWC.
- December 16, 2002.
- Kathy Riley and Laura Carlson.
Usability Test Team Members.
- Kathy Riley, principle investigator CSIDP.
- Laura Carlson.
- Barb Johnson.
- Jo Mackiewicz.
- Bruce Reeves.
- Craig Stroupe.
Projected Timetable.
Goal: Go live with new site by September 1, 2003.
Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | |||
---|---|---|---|---|---|---|---|---|---|---|
Round I: Test the current site
|
x | x | x | |||||||
CWC: Incorporate findings
|
x | |||||||||
Round II: Test the 1st version of the new template
|
x | x | ||||||||
CWC: Incorporate findings
|
x | |||||||||
Round III: Test the refined version of the new template
|
x | x | ||||||||
CWC: Incorporate findings
|
x |
Projected Budget:
- Operating expenses (approx): $700.
- Contibution from CSIDP: -$350.
- Contibution from ITSS: -$350.
- Estimated Budget Breakdown.
Information needed from CWC:
- Additional survey results.
- Other known likes/dislikes/problems.
- Specific testing areas.
- Specific target groups.