Campus Construction Updates - March 21, 2012

Welcome
Over the summer months elevator upgrades across campus will be the main cause of changes in access to floors. We hope the table below will help you plan where to go to reach your destination.

A new map will be posted with information about construction when available.

UMD Elevator Groups

Out of Service

Return to Service

Alternate Route During Outage

 

 

 

 

Group 1

 

 

 

Tweed Museum

5/14/2012

7/27/2012

Humanities and Cina Elevators

Kirby Student Center (small passenger elev)

4/30/2012

7/9/2012

Solon Campus Center Elevator

Kirby Plaza (small passenger elevator)

4/2/2012

8/1/2012

Bohannon and Solon Campus Center Elevators

Group 2

 

 

 

Darland Administration Elevs 1 & 2

5/14/2012  Elev 1 7/9/2012 Elev 2

6/29/2012 Elev 1  8/15/2012 Elev 2

Elevators will be done one at a time. Use alternate elevator.

Residence Dining Center

5/28/2012

6/22/2012

Solon Campus Center Elevator

Group 3

 

 

 

Montague Hall

5/7/2012

8/8/2012

Bohannon Elevator for Ground and 1st floors.  Second floor inaccessible by elevator.

Heating Plant

5/7/2012

7/31/2012

N/A

Lund Building

5/14/2012

7/30/2012

N/A

Group 4

 

 

 

Sports and Health Center

6/25/2012

8/15/2012

 

Library Annex

6/25/2012

8/15/2012

Library Elevators

Group 5

 

 

 

Lake Superior Hall Elevs 1 & 2

6/11/2012 Elev 1      7/2/2012 Elev 2

6/29/2012  Elev 1 7/20/2012  Elev 2

Elevators will be done one at a time. Use alternate elevator.

Cina

5/21/2012

6/8/2012

Humanities Elevator for Ground, 1st and 2nd floors.  Third floor inaccessible by elevator.

Chemistry

6/1/2012

6/8/2012

Ground Floor accessible off the main concourse.  Med School Elevator for 2nd Floor.  Third floor inaccessible by Elevator.

Group 6

 

 

 

MPAC Stage Lift

TBD

TBD

TBD

New Construction

 

 

 

Cloquet Forestry Center

9/24/2012

10/26/2012

N/A

EduE Building

5/15/2012

8/15/2012

N/A